Dromadda
More wind farm has planning permission for 11 turbines and it has
secured grid capacity of 32 MW in 'Gate 2' and 'Gate 3' of the
Group Processing Scheme run by the Commission for Energy Regulation
(CER). When constructed, the project will generate 132 million
kWh of green electricity per year - enough to power almost 30,000
energy efficient homes. This would result in savings of approximately
95,000 tonnes of CO2 emissions per year. The project
will commence construction in 2014 and is due to be energised in
2015.
|